How Long Do Home Remodels Take?

Theoretically, only a specialist can give you a fair answer to this question, depending on the complexity of the works: the number of rooms to be remodeled, the type of work (major repairs or simpler operations), but also the number of workers and their experience. The more trained and responsible staff is available - look at this site http://www.swiftbuildersllc.com/ -, the faster and better the remodeling work will be accomplished.

Some general estimates

  • Demolition (complete removal of walls and ceilings) - How long such an operation takes depends on the surface of the house and the complexity of the work. Basically, it takes about 3 to 14 days
  • Partitioning - If it does not require breaking walls, it will last for 1-2 days
  • Switching electrical installations + electric panel: about 2-3 days
  • Change of sanitary and heating installations: about 2-3 days
  • Changing carpentry: 1-2 days
  • Flooring: 2-7 days, depending on the required operations and the surface
  • Painting, wallpapering, siding: from 3 days to 1-2 weeks
  • Installation of sanitary items and electrical appliances takes about 1 day of work
  • Assembling custom furniture (kitchens, libraries, dressings, etc.): 1-2 days
  • Installing accessories and cleaning the house: 2-3 days

You can now make an estimate of the remodeling work, although you can expect at more variables. If your home remodeling includes everything we have described above, it will take about two months of full time work to accomplish the project.

Article Source right here: How Long Do Home Remodels Take?

Comments

Popular posts from this blog

Fort Collins Basement Remodeling – Extending Your Living Space 

How Home Remodeling in Fort Collins Can Transform the Way You Live

How to Generate Inspiration for Your Remodeling Project